Estimate drainage stone for excavation dimensions you already have. Subtract chamber displacement to find the stone fill volume.
Your estimate
YOU NEED
—
≈ —
Estimate breakdown
Excavation volume
—
Chamber displacement
—
Net stone before allowance
—
Allowance
—
Final order volume
—
Weight is an estimate. Stone grading, bulk density and moisture vary; confirm the product and order quantity with your supplier.
How to use this calculator
Enter the planned excavation dimensions and, for a chamber or crate, its dimensions. The calculator subtracts chamber displacement from the excavation volume to estimate the stone fill. Your allowance changes only the final stone quantity.
What does this measure?
Excavation volume − chamber volume = net stone fill volume. The chamber is not counted as stone.
What stone should I use?
Drainage projects commonly use clean, washed stone. Follow the chamber manufacturer, installer, engineer or applicable local project requirements; no single stone type fits every installation.
Does this size my dry well?
No. This estimates stone quantity for dimensions you already have. It does not determine stormwater storage capacity, infiltration performance, soil suitability or code compliance.
Worked example
An 8 × 8 ft excavation, 5 ft deep, with a 4 × 4 × 4 ft rectangular chamber and no allowance:
Excavation volume
320.00 ft³ · 11.85 yd³ · 9.06 m³
Chamber displacement
− 64.00 ft³ · 2.37 yd³ · 1.81 m³
Net stone requirement
256.00 ft³ · 9.48 yd³ · 7.25 m³
Dry well stone questions
How much stone do I need around a dry well chamber?
Enter the excavation and chamber dimensions. The estimate subtracts chamber displacement from excavation volume, then applies only the allowance you select.
Does this calculator size the dry well for my roof?
No. It estimates stone quantity for dimensions you already have. It does not assess stormwater capacity, infiltration performance, soil conditions or code compliance.
Does the stone allowance include compaction?
No. Allowance is an optional extra for measurement differences and irregularities. It is not a compaction factor.
Why is chamber volume subtracted?
The chamber occupies part of the excavation, so stone fills only the remaining volume around it.